In the interests of public safety it will be necessary for Oxfordshire County Council to close footpath 230/6/30 for demolition and replacement of the cradle footbridge.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 30 September 2024. The estimated completion of the works is 6 December 2024, 24 hours per day.
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)
Notice of intention to make the Order will be published in the local press.
Access will be maintained for emergency service vehicles and for those frontages within the closure area, subject to the progress of the works and liaison with the works supervisor.
A copy of the drawing showing the extent of the closure and the alternative routes for traffic is attached.
Further information regarding the works may be obtained by contacting Kieran Beausire-Bridges Team Oxfordshire County Council on 0345 310 11 11.or email [email protected]
T14210 / RAG
One Network Fix My Street | Regards Robert Graham Officer (TTRO Team) Network Co-ordination 07741 607617 Oxfordshire County Council, Ron Groves House , Oxford Road, Kidlington , Oxfordshire, OX5 2BP www.oxfordshire.gov.uk |